DESCRIPTION OF PROJECT:

Klong Prapa is generally a canal utilized for supplying raw water. Krom Klong Prapa Road, a royal contemplate project, was originated to improve raw water supplying as well as to serve extension of city civilization and also traffic congestion problem in urban area. Chaengwattana underpass is one part of this project. AEC awarded the contract to the IEC to carry out the detailed engineering design of underpass to deal with such a major concern. The typical scope of work consists of design of one underpass, civil work design.

SCOPE OF SERVICES:

·         Detailed engineering design of underpass as follow:

-       Superstructures and substructures

-       Retaining wall and base slab

-       Foundation analysis & design

-       Approach structures and transition units

 

KEY FACTORS:

·         Geotechnical and structural design of Retaining wall, base slab, pilings and piled foundation of the underpass.

·         Preparation of drawings, specifications & calculations