CHIENGMAI UNDERPASS HWY NO. 11 INTERSECT WITH HWY NO. 107 & 118
LOCATION : Chiengmai, Thailand
CLIENT : Jirathep Partmership limited
PERIOD OF SERVICES: Geotechnical Instrumentation: May 2006 – Aug 2006
CAPITAL COST : 1,00,000.00 Baht
FINANCED BY: N/A
ASSOCIATED FIRMS: N/A
DESCRIPTION OF PROJECT: According to the rapid growth rate of Chiengmai province and in order the serve the future traffic demand, the infrastructure system of province is concerned. Underpass is one of the most well-known methods to deal with the future traffic congestion. Jirathep partnership limited was awards to be contractor. The work involved to deep excavation, thus safety and movement of retaining structure are therefore a major concern both of during construction and long term period. The installation and monitoring work of geotechnical instrumentation were required and carefully monitoring. The monitoring data is used to assess the effects of construction and to avoid the possible damage due to ground movement. .
|
SCOPE OF SERVICES:
KEY FACTORS:
|